Key Stats

Concrete Poured: 4,300 m3
Kerbs & Edging: 3,585 m
Steel Reinforcement: 94 t mesh & loose bar

Project Information

Hennigan Building & Civil Engineering Ltd were awarded the majority of the groundworks package for the new Eddie Stobart Distribution Facility as part of the Midlands Logistic Park Development for Volker Fitzpatrick. Our works included, foundations, dock leveller slabs, retaining walls, Q-max linear drainage, external works which also included a 15,500m2 car park. The groundworks for 844,000 square foot facility & external works were let on one continuous visit which we completed within our client’s programme requirements.